Quimby House
 Design that we picked
Floor Plan
We mirrored it
Driveway Dig
Uploaded June 11 2002
Basement Dig
August-24-02

[Click to enlarge image] [Click to enlarge image] [Click to enlarge image]
Footings
Uploaded Aug 30 2002
Land Leveling
Uploaded Sep 12 2002
Forms
For the basement walls
9/16-9/19 2003
Pouring Basement Walls
Sept 20 2002
[Click to enlarge image] [Click to enlarge image]
Basement Plumbing
Sept 27 2002
Basement Floor
Oct 8 2002
Steel Beams
Oct-18-2002
Framing
Oct 21 - Nov 22 2002